top of page

PROJECT

SPOTLIGHTS

Finished photos ©️ Inside the Eye Photography by Michael Finizia 

Rollhouse - North Olmsted

Location: 24488 Lorain Rd., North Olmstead OH    

Completed: December 2023

Type: Renovation, Entertainment

This project entailed remodeling an existing bowling alley into a more 
comprehensive entertainment center.  All entrances, food service, restrooms and 
concourse areas were gutted and reconstructed.  Electrical service was upgraded 
and much of the HVAC system was replaced with new.  An integrated energy 
management system was introduced, and a new VIP bowling party center area was 
created for private parties and events.  The earlier dining and kitchen areas were 
constructed on a raised slab that was removed during the remodel so that all 
portions of the concourse, dining, administrative, and common areas were at a 
single elevation. 
 
Due to the age of the building, very few existing drawings were available.  This led 
to the discovery of several unforeseen structural support conditions being 
uncovered during construction that all had to be addressed.  Reconfiguration of the 
project floor plan and creative shoring and structural support solutions were the 
primary tools used to overcome these issues.   The facility always remained open 
throughout construction with a minimum of 60% of the lanes available.  

Notre Dame Cathedral Latin - Middle School

Location: 13000 Auburn Rd. Chardon Ohio 44024      

Completed: February 2025

Type: Renovation, Educational

 

This project involved renovation of an existing Sisters of Notre Dame dormitory living space, into a new Middle School on the second floor of an existing 3-story masonry building. The space is now complete with classrooms, science labs, added offices, renovated restrooms, a collaboration space for students to socialize with faculty, conference rooms and upgraded life safety to achieve code compliance. The scope of work included demolition, asbestos abatement, masonry, miscellaneous metals, rough and finish carpentry, millwork, fireproofing, specialty-stained glass, glass and glazing, doors, frames & hardware, interior partitions, acoustic ceilings, resilient flooring, resinous flooring, paint, miscellaneous specialties, lockers, plumbing systems, HVAC systems, Electrical and Fire Alarm.  
 
The project posed specific challenges due to the age of the structure and need to abate and then fire-proof much of the existing structure. We were able to complete abatement and fireproofing over the summer while school was not in session, but much of the renovation was completed during the fall 2024 school semester and we were working directly overhead existing occupied classroom spaces. We successfully completed the project on our original schedule, WITH an added 3,800sf of added scope, a challenge for our project team that they met with vigor. 
 
Significant scope additions were approved to be added to the original GMP, adding an entire 
West wing to the space, once the owner received added funding. The owner was able to add 
approximately 3,780sf of finished classroom and office space through these West Wing scope 
additions, for a net total of approximately $81/sf, after credits (deducts) in allowance and 
contingency savings. 

Lake House Elevator Modernization

Location: 11850 Edgewater Drive, Lakewood Ohio – 44107

Completed: June 2024

Type: Private Elevator Modernization

 

This was a private competitive GC bid process to modernize three (3) eleven (11)-stop elevators at a high-rise condominium complex on the Lake in Lakewood. The project was phased due to the necessity to maintain elevator traffic for the building. Two of the elevators were passenger elevators and the third was a freight elevator, all with basement access. This forced the project along a phased path where one elevator and hoist way was demolished and modernized at one time, while we attempted to take advantage of work crews and equipment availability to prepare for subsequent phases of work ahead of time. For instance, we performed hoist way steel cleaning and masonry repairs for all three elevators at one time and merely targeted low traffic times to perform the work, shutting down one hoist way at a time to ride all eleven stops. While the phased nature of the work allowed for procurement float in the schedule, the first modernization schedule was on the critical path and there were challenges with obtaining the penthouse elevator equipment.

 

The project began with the replacement of one of the passenger elevators in May 2023. We anticipated 4-6 months per elevator, and the first elevator required 7-months before it was operational and fully inspected. After completion of the first elevator, we were able to complete the 2nd passenger elevator and the freight elevator in a shorter span, due to completing the penthouse and hoist way work scopes in the first phase. We completed the modernization of the final two elevators in just 8 months total, for an overall project duration of 13 months. Work scope included selective interior demolition, complete demolition of the penthouse, concrete repairs in the pit and penthouse, masonry repairs in the penthouse and hoist ways, steel cleaning and miscellaneous metals (stainless steel finishes), a custom Unistrut and steel partition in the penthouse for the existing boilers, rough carpentry blocking, new fire-closet doors and hardware, a new penthouse door and frame, framing, drywall, plaster work at the new telecom/fire closet, new interior cab floor finishes, removed wall coverings at each elevator lobby entry and subsequent plaster refinishing and paint, new elevators and related equipment, new mini-split systems to supply the multi-level penthouse, electrical power for modernized equipment and HVAC, updated lighting, and a new FA annunciator panel and devices.

 

The original project schedule was 18-months, allowing 6-months per elevator, but only required 13-months on site plus 5-months procurement, so the project was finished within the schedule allowance and the work on site finished well before the allowed timeframe. The original project scope was completed under budget and for this reason, the owner elected to add some small scopes on via change order and all of the miscellaneous change order scope was completed within the original project time frame and under 10% of the cost of the original budget. The project was very successful, kept a carpenter employed for over a year on this dedicated work, and proved to be a collaborative effort between the client’s facilities team, the elevator contractor, the designers, and Lawler Construction.

 

Our work was so fluid, and we seamlessly blended into the owner’s normal operations that the owner was even able to complete adjacent projects related to their underground parking garage, pool deck improvements, and improvements to their generator systems, all while one elevator was constantly unavailable to be modernized.

CWRU Millis Labs

Location: 2074 & 2076 Adelbert Rd, Cleveland, Ohio 44106

Completed: Feb. 2026

Type: Educational, Laboratory, Renovation

 

Scope:

Awarded via competitive bid in mid-2025, these projects included a full scope of lab gases, fume hoods and specialized electrical requirements.  At a combined value of almost $2MM, the projects represent four separate groups of labs coupled with additional space for graduate students to gather, work and study.  The projects were bid by the owner with the intent to award and construct both simultaneously.  Work commenced in September, 2025.

 

The projects involved the complete gutting and abatement of multiple existing laboratory spaces including some adjacent offices.  With fully occupied buildings, staging was a concern at both locations and required a good deal of planning and coordination.

 

As with many laboratory projects, the amount of vertical clearance in combination with the density of overhead utilities resulted in open ceiling designs.  Since these were existing laboratory spaces, much of the routing of utilities was pre-ordained by the location of existing utility lines and branches.  With multiple fume hoods, new air valves and heating coils, extensive ductwork and multiple different lab gases, deionized water and a vacuum system, there was still a good deal of coordination required to avoid conflicts.  We opted to assign “air rights” to each trade providing them with a vertical section of the space within which we requested that they maintain all their piping and ductwork.  This resulted in less and less serious conflicts.  The projects did not include any new exhaust fans which simplified and speeded up our ability to install the work. 

 

There were a couple of major delay items that ended up creating an overall later delivery of about a month.  The owner worked with us on all items and we were able to deliver all of the projects for use in early February, 2026.  Due to good Owner planning and the inclusion of appropriate contingencies on both projects, they were both able to remain within budget.  Almost all changed and added work was able to be paid for through use of the allowances.   

 

The laboratories are in service and operating as planned.  We look forward to working with Case and other owners on many future lab projects.

Favorite Final Red, Black, Grey (1).png

© 2022 Lawler Construction, LLC

bottom of page